As a subcontractor to the Turner Acura Lindahl Triventure, McDonagh demolition installed nine manhole and catch basin structures with pipe runs from 18” to 54” as well as 46,368LF of underdrain with 137 inspection hole structures placed along the new runway and taxiways. McDonagh was also responsible for extensive removal operations including electrical ductbank from 2-way to 44-way, lift stations, drainage pipe, and electrical and sewer structures.

This work was performed under a demanding and tightly coordinated schedule. Two 30-day closures were included in the project each presenting difficult schedule requirements which were met by McDonagh Demolition’s crews

This project began for McDonagh in June of 2014 and will be completed in the Spring of 2015.